Data Centre Delivery in Just 7 Months

Urbacon delivered the 12,000 SF PSINet (later Telus) operations centre in just seven months—nearly four months ahead of schedule. Despite design evolving during construction and challenges like residential proximity, existing tenants, and complex tech requirements, the project was completed with custom high-tech interiors and structural upgrades. Our performance led to further Telus contracts for power, UPS, and fuel system enhancements.

Info Project

Location
  • Toronto, Ontario
MEGAWATTS
  • 5.0MW Of Critical Power
Square Feet
  • 201,000 SF
Completion Date
  • May, 2002