TORONTO DC2: Accelerated Customization & Sustainable Innovation
Toronto DC2 exemplifies rapid delivery and client responsiveness. We completed the site’s shell and all approvals before leasing, allowing for swift, tenant-specific customization. As a result, DC2 achieved Ready for Service just 118 business days after contract signature, setting an industry pace for projects of this scale. DC2 also continued UDCS’s commitment to sustainability as the first Canadian hyper-scale data centre to use reclaimed rainwater for evaporative cooling and onsite reserves. This proactive approach and deep development knowledge ensured flexibility, reliability, and regulatory compliance, delivering resilient, sustainable infrastructure tailored to evolving client needs.





Prev
Next
Project Info
Location
- Richmond Hill, Ontario
MEGAWATTS
- 12 MW of Critical Power
Square Feet
- 105,000 SF
Completion Date
- October, 2020